Antenna towers, siting rules and Safety Code 6 when you buy a wireless internet provider
Only the federal Minister of Industry has the authority to approve tower sites, and the Radiocommunication Act, subject to regulations under section 6, lets the Minister approve each antenna site and the erection of masts and towers; ISED’s circular says parts of its process are ongoing obligations of owners and operators of existing antenna systems.
The towers and antenna sites of a wireless internet provider are regulated federally, and the rules do not stop applying on the day a business is sold. This article walks through the federal rules a buyer meets at the physical sites: who approves them, what stays with existing antenna systems, sharing, local consultation, exclusions, radiofrequency exposure, aviation marking and radio licences. Ask a lawyer whether any provincial or municipal rule touches the sites you are looking at. For the deal as a whole, see buying an ISP or rural broadband provider in Canada.
Why tower sites are a federal matter
Paragraph 5(1)(f) of the Radiocommunication Act lets the Minister approve each site on which radio apparatus, including antenna systems, may be located, and approve the erection of all masts, towers and other antenna-supporting structures. That power is subject to any regulations made under section 6 of the Act, and the Minister acts taking into account all matters the Minister considers relevant for ensuring the orderly establishment or modification of radio stations and the orderly development and efficient operation of radiocommunication in Canada. ISED’s antenna circular restates the point in its section 1.1: the Minister may approve the erection of all masts, towers and other antenna-supporting structures, taking into account all matters the Minister considers relevant for ensuring the orderly development and efficient operation of radiocommunication in Canada.
ISED’s consultation notice on tower siting says that only the federal Minister of Industry has the authority to approve tower sites, under paragraph 5(1)(f) of the Act. The same notice says that concurrence of the local land-use authority is an important aspect of the tower siting process, because land-use authorities represent local concerns about land use in their communities. It lists the Minister’s powers under the Act as approving tower sites and the construction of antenna-supporting structures, planning the allocation and use of spectrum, issuing spectrum licences, fixing the terms and conditions of licences and amending the terms and conditions of any spectrum licence. When you read a seller’s list of sites, treat each tower and antenna location as something to check on its own.
Obligations that stay with existing antenna systems
ISED’s antenna circular says that parts of its process contain ongoing obligations that apply to existing antenna system owners and operators. The circular also says that installing an antenna system, or operating a currently existing antenna system, in a way that is not in accordance with the process may result in its alteration or removal and other sanctions against the operator, in accordance with the Radiocommunication Act. Those statements matter to a buyer who will become the operator of the sites.
The circular says proponents and operators of existing antenna systems must retain copies of all information related to Safety Code 6 compliance, such as analyses and measurements. In its section on sharing, the circular says parties should retain records, such as analyses, correspondence and engineering reports, relating to that section. Ask the seller for those files for every site, and for any correspondence with ISED or a local authority about the sites.
Sharing existing towers and sites
Section 3 of the circular says that, before building a new antenna-supporting structure, ISED requires proponents to first explore a set of options. The broad elements of the process include investigating sharing or using existing infrastructure before proposing new antenna-supporting structures. A proponent is not normally expected to build a new antenna-supporting structure where it is feasible to locate an antenna on an existing structure, unless a new structure is preferred by the land-use authority.
The same circular says owners and operators of existing antenna systems are to respond to a request to share in a timely fashion and to negotiate in good faith to facilitate sharing where feasible. ISED anticipates that 30 days is a reasonable time for an existing owner or operator to reply in writing to a proponent’s request, with either a proposed set of reasonable terms to govern the sharing of the antenna system or a detailed explanation of why sharing is not possible. The circular points to Client Procedures Circular CPC-2-0-17, on conditions of licence for mandatory roaming and antenna tower and site sharing and to prohibit exclusive site arrangements. If the provider you are buying owns towers, ask the seller whether sharing requests have been made, how each was answered and whether any sharing agreement exists.
New or modified towers: local consultation and the 120-day period
Proponents must always contact the applicable land-use authorities to determine the local consultation requirements and to discuss local preferences on antenna system siting or design, unless their proposal falls within the exclusion criteria in section 6 of the circular. Unless the proposal meets those exclusion criteria, proponents must consult with the local land-use authority on any proposed antenna system before any construction. If you plan to add or change a tower after closing, this is the process you would be starting. The circular’s main steps follow.
- If the land-use authority has designated an official to deal with antenna systems, proponents are to engage the authority through that person.
- Where no established agreement exists between land-use authorities, proponents must, as a minimum, contact the land-use authority or neighbouring land-use authorities within a radius of three times the tower height, measured from the tower base or the outside perimeter of the supporting structure, whichever is greater.
- Proponents must follow the land-use consultation process for the siting of antenna systems established by the land-use authority, where one exists.
- If a land-use authority’s existing process has no public consultation requirement, proponents must fulfil the public consultation requirements in ISED’s default public consultation process.
- Telecommunications carriers, broadcasting undertakings and third party tower owners must notify and consult with the local public when proposing a new antenna tower, either by following ISED’s default process or, where one exists, the land-use authority’s process.
ISED expects land-use consultation to be completed within 120 days from the proponent’s initial formal contact with the local land-use authority. Depending on individual circumstances, ISED may support additional time or consider the land-use authority consultation process concluded. The circular also says the 120-day consultation period commences only once proponents have formally submitted, in writing, all plans required by the land-use authority, and does not include preliminary discussions with land-use authority representatives.
Under ISED’s default public consultation process, it is the proponent’s responsibility to ensure that the notification provides at least 30 days for written public comment. A proponent of an antenna system proposed to be 30 metres or more in height must also place a notice in a local community newspaper circulating in the proposed area, and in areas without a local newspaper other effective means of public notification must be implemented. If the local public or the land-use authority raises a question, comment or concern as a result of the notification, the proponent must clearly indicate in its response that the party has 21 days from the date of the correspondence to reply. The proponent may only start installing or modifying an antenna system after the consultation process has been completed by the land-use authority, or ISED confirms concurrence with the consultation portion of the process, and after all other requirements under the process have been met.
Exclusions from consultation
The circular excludes some proposals from land-use authority and public consultation requirements. All proponents must still satisfy the general requirements in section 7 of the circular, whether or not an exclusion applies to their proposal. Among the exclusions are the following examples.
- The exclusion for existing antenna systems covers modifications, added antennas and tower replacements, including to facilitate sharing, provided the total cumulative height increase stays within a limit the circular sets as a share of the height of the initial antenna system installation, and a replacement must be similar to the original design and location. No increase in height may occur within one year of completion of the initial construction, and this exclusion does not apply to antenna systems using purpose built antenna supporting structures with a height of less than 15 metres above ground level operated by telecommunications carriers, broadcasting undertakings or third party tower owners. Ask the seller for the first consulted or installed height of each structure and every change made since.
- Non-tower structures, such as buildings, water towers and lamp posts, may be excluded from consultation provided that the height above ground of the non-tower structure, exclusive of appurtenances, is not increased beyond a limit the circular sets as a share of that height. Ask the seller for the height of each such structure before and after the antennas went on, and check it against the circular.
- The exclusion for new antenna systems where the height is less than 15 metres above ground level does not apply to antenna systems proposed by telecommunications carriers, broadcasting undertakings or third party tower owners.
The circular advises proponents who are not certain whether their proposals are excluded, or whether consultation may still be prudent, to contact the land-use authority or ISED for guidance. Do the same for any past or planned change at a site you are buying, and ask the seller for what was done.
Safety Code 6 and radiofrequency exposure
The circular says that while the responsibility for developing Safety Code 6 rests with Health Canada, ISED has adopted the guideline for the purpose of protecting the general public. The code specifies maximum levels of human exposure to radiofrequency fields at frequencies between 3 kHz and 300 GHz, to prevent adverse human health effects in both controlled and uncontrolled environments. The Code defines uncontrolled environments as areas where either insufficient assessment of radiofrequency fields has been conducted, or where persons allowed access have not received proper awareness or safety training and have no means to assess or, if required, to mitigate their exposure. The Code says it is periodically revised to reflect new knowledge in the scientific literature, and that the exposure limits may be modified if deemed necessary.
The circular says it is the responsibility of proponents and operators of installations to ensure that all radiocommunication and broadcasting installations comply with Safety Code 6 at all times, including consideration of the combined effects of nearby installations within the local radio environment. Compliance is an ongoing obligation. At the request of ISED, telecommunications carriers and operators of broadcasting undertakings must provide detailed compliance information for individual installations within 5 days of the request. At any time, antenna system operators may be required, as directed by ISED, to demonstrate compliance by providing detailed calculations, by conducting site surveys, or both, and, where necessary, by implementing corrective measures.
Telecommunications common carriers and operators of broadcasting undertakings are to carry out an exposure evaluation on all new installations and following any increases in radiated power. Where emission reaches a share of the Safety Code 6 limits for uncontrolled environments that the circular sets, at locations accessible to the general public, the operators of radio frequency emitters must notify ISED and demonstrate compliance with Safety Code 6. Ask the seller for the latest exposure evaluation for each site and whether any site has reached that level. For proponents following ISED’s default public consultation process, the notification package must provide a written attestation that there will be compliance with Safety Code 6 for the protection of the general public, including consideration of nearby radiocommunication systems. That package must also indicate any Safety Code 6 related signage and access control mechanisms that may be used.
Health Canada’s explainer says ISED oversees the licensing and placement of cell towers and ensures that these towers comply with the regulatory standards for human exposure limits outlined in Safety Code 6. It adds that ISED maintains a market surveillance program and routinely audits antenna installations and devices to verify compliance. Ask the seller for the compliance analyses and measurements for each site, and ask your own engineer whether they are current.
Marking and lighting of towers
The circular says proponents must ensure their proposals for any antenna system are first reviewed by Transport Canada and NAV CANADA. Transport Canada will perform an assessment of the proposal with respect to the potential hazard to air navigation and will notify proponents of any painting or lighting requirements for the antenna system. Proponents should be aware that Transport Canada does not advise ISED of marking or lighting requirements for proposed structures. As required, the proponent must include any Transport Canada marking or lighting requirements in the public notification package.
Section 601.24(1) of the Canadian Aviation Regulations says that any person who plans to construct or modify a building, structure or object, or launch a tethered object, shall notify the Minister of the proposed construction, modification or launch in accordance with the requirements of Standard 621 if the building, structure or object, or tethered object, will constitute an obstacle to air navigation; in those Regulations, the Minister means the Minister of Transport. Ask the seller which towers were reviewed, what marking or lighting was required and whether it is in place today.
Radio licences and proposed changes to the siting process
Section 11 of the Radiocommunication Regulations makes it a term of a radio licence that the licence not be transferred or assigned without the authorization of the Minister. So the licences used at the sites are a separate question from the sites themselves. For the licence side of a purchase, see what licences transfer when you buy a business.
ISED has initiated a consultation on proposed amendments to the antenna tower siting requirements found in CPC-2-0-03, to reduce regulatory burden on tower proponents. That is a proposal, not the operative rule. The notice describes current practice in its paragraph 37: when a land-use authority does not concur with an antenna tower proposal, ISED encourages the proponent and the authority to find a mutually agreeable solution to the authority’s concerns. If discussions are not fruitful, either party can signal an impasse to ISED, which will request and review all information from both parties and make a final decision as to the tower’s location. Ask a lawyer to confirm the current siting requirements for each site before you close.
Questions to ask before you buy
- Can the seller list every tower, mast and rooftop site, say who owns each structure and show the approvals for each?
- Which sites were built or changed, and did each go through local consultation or fall within an exclusion?
- Where are the exposure analyses and measurements for each site, and when were they last updated?
- Has ISED ever audited, questioned or directed the provider about any installation?
- Have other parties asked to share a tower or site, and how were those requests answered?
- What marking or lighting does each tower need, and is it in place?
- Which radio licences are used at each site, and has the seller asked the Minister about authorization to transfer them?
Questions people ask
Short answers; each links to the full page.
- What am I buying when I buy a wireless internet provider?
- You are buying a bundle of agreements, equipment and relationships: tower and rooftop site leases, radios and customer equipment, upstream backhaul, the subscriber list, billing and support systems, the people who install and fix it, and any licence holdings. Each piece needs its own check, and some may need consent to transfer. Ask your lawyer. Full answer
- How do I find an internet service provider or WISP for sale in Canada?
- Small internet providers rarely advertise openly, so use several routes at once: listing sites and brokers, industry associations and equipment suppliers, neighbouring providers, and direct approaches to owners. Expect a listing to withhold the network map and subscriber detail until you sign a confidentiality agreement. Full answer
- What should I check in the lease before buying a business?
- Read the assignment clause, the remaining term and renewal options, the rent and any escalation schedule, the permitted use, and whether the current owner has given a personal guarantee. For a location-dependent business, an unfavourable lease can undermine an otherwise sound purchase, so review it early. Full answer
Related reading
10 pages on the same subject, grouped by topic.
Due diligence
- GuideDue diligence on an ISP or rural broadband provider
- Expert answerHow do I check a telecom installer’s test sets and tone tracing gear?
- Expert answerWhat test equipment should a network cabling company own and keep calibrated?
- Expert answerHow do I assess the skill mix of a cabling crew, such as fibre splicers?
Sources
Every requirement and figure referenced in this guide traces to a primary source. Links were last confirmed on the dates shown.
- 01Innovation, Science and Economic Development CanadaGovernmentCPC-2-0-03 — Radiocommunication and Broadcasting Antenna Systems
- 02
- 03Health CanadaGovernmentUnderstanding Safety Code 6: Health Canada’s radiofrequency exposure guidelines
- 04Government of Canada (Department of Justice)GovernmentRadiocommunication Act (R.S.C., 1985, c. R-2)
- 05Government of Canada (Department of Justice)GovernmentCanadian Aviation Regulations (SOR/96-433)
- 06Government of Canada (Department of Justice)GovernmentRadiocommunication Regulations (SOR/96-484)
- 07Innovation, Science and Economic Development CanadaGovernmentConsultation on Amendments to the Tower Siting Process and Decision on Roaming, Tower Sharing and Annual Reporting Requirements for Terrestrial Licences
Deavo is an advertising and listings platform, not a brokerage, law firm or valuation firm. This page is general information, not legal, tax, accounting or valuation advice, and rules differ by province. Confirm anything you rely on with a qualified professional before you act on it.