Alberta prompt payment and adjudication rules when you buy a construction contractor

A tradesperson measures a wooden frame in a workshop lined with power tools.
Photo by Ryno Marais on Unsplash

In Alberta, an owner who owes money under a proper invoice must pay no later than 28 days after receiving it, subject to the owner’s notice of dispute. Provided no court application about the dispute has been started, a subcontractor not paid within the required timeline may issue a Notice of Adjudication.

In Alberta, the owner’s duty to pay a proper invoice within 28 days, the owner’s right to dispute it within 14 days, and the adjudication process for payment disputes all sit in the same body of rules. A buyer of an Alberta construction contractor can ask which of those timelines each receivable and payable runs on. This guide walks through the Alberta rules in the order a payment moves down the chain, then public work, then the questions to put to the seller about the receivables ledger.

It covers Alberta only. It does not say how much a contractor’s receivables are worth or whether any deal should go ahead. For lien and holdback questions elsewhere, see the glossary entry on construction holdback and ask a lawyer where the project is.

What Alberta’s prompt payment rules set out

Alberta.ca says prompt payment rules establish payment timelines and an adjudication process for contractors and subcontractors. The timelines for the construction industry, the timelines for filing liens and the rules for adjudication in a payment dispute are outlined in the Prompt Payment and Construction Lien Act, the Prompt Payment and Adjudication Regulation and the Forms Regulation. Alberta.ca adds that amendments to the Prompt Payment and Adjudication Regulation were passed in late 2025.

Alberta.ca says all new construction contracts in Alberta must adhere to the rules of the Prompt Payment and Construction Lien Act as of August 29, 2022. Existing contracts that extend beyond August 29, 2024 had to become compliant by August 29, 2024. When a contract was signed is therefore a question to put to the seller for each project in the ledger. Alberta.ca says amendments to the Prompt Payment and Adjudication Regulation were passed in late 2025. Ask a lawyer to confirm the current text before you rely on a figure or a form in it.

Proper invoices and the 28-day payment clock

The clock starts with a proper invoice. Alberta.ca says project owners must pay the amount payable to contractors within 28 calendar days of receiving a proper invoice. Section 32.2(1) of the Prompt Payment and Construction Lien Act says an owner who owes money under a proper invoice must pay no later than 28 days after receiving it. That duty is subject to subsection (2), which deals with the owner’s notice of dispute.

The Act defines “proper invoice” for the purposes of its Part. Among the items section 32.1 lists, a proper invoice must state the date of the invoice and the period during which the work was done or materials were furnished, and must include a statement that it is intended to constitute a proper invoice. Alberta.ca’s list of what proper invoices must contain includes the contractor’s name and business address and the date of the invoice. These are examples from longer lists, so a buyer should ask a lawyer for the full set.

Under section 32.1(5), a proper invoice may be revised if the parties to it agree to a revision, the date of the proper invoice is not changed, and the invoice continues to meet the requirements. Alberta.ca says a revised proper invoice keeps its original date.

Section 32.1(6) says that, subject to the regulations, proper invoices must be given to an owner at least every 31 days, unless the contract includes testing and commissioning and the conditions of testing and commissioning are not met.

Notices of dispute and notices of non-payment

Under section 32.2(2), an owner who disputes a proper invoice may refuse to pay all or part of it within the 28-day period if, no later than 14 days after receiving it, the owner gives the contractor a notice of dispute. The notice is given in the prescribed form and manner. It specifies the amount of the proper invoice that is not being paid and details all the reasons for non-payment. Subsection (1) continues to apply to any amount payable under the invoice that is not disputed. Alberta.ca says the same on timing: an owner disputing an invoice must give notice to the contractor within 14 calendar days of receiving it.

Under the Act, the owner’s notice to the contractor is a notice of dispute under section 32.2(2), while a contractor’s notice to a subcontractor is a notice of non-payment under section 32.3(6). In a ledger, ask which notice each document is and who gave it.

Down the chain, section 32.3(1) says that, subject to the giving of a notice of non-payment under subsection (6), a contractor who receives full payment of a proper invoice within the owner’s deadline must, no later than 7 days after receiving payment, pay each subcontractor the amount owed. If the owner does not pay some or all of a proper invoice on time, section 32.3(4) says the contractor must, subject to subsection (5) or (6), pay each subcontractor no later than 35 days after giving the proper invoice to the owner, to the extent the subcontractor was not paid in full.

Section 32.3(5) lifts the contractor’s duty under subsection (4) for a subcontractor if, by the deadline in subsection (7), the contractor gives that subcontractor a notice of non-payment in the prescribed form stating that some or all of the amount is not being paid due to non-payment by the owner, an undertaking to refer the matter to adjudication no later than 21 days after giving the notice, and a copy of any notice of dispute the owner gave. Under section 32.3(6), a contractor who disputes a subcontractor’s entitlement may refuse to pay all or part of it if the contractor gives the subcontractor a notice of non-payment, in the prescribed form and manner, specifying the amount not being paid and detailing all the reasons. That notice is due within 7 days after the contractor receives the owner’s notice of dispute or, if the owner gave none, before the 35-day period in section 32.3(4) expires. Section 32.4(1) adds that, subject to the regulations, a contractor who receives an owner’s notice of dispute must, without delay, advise its subcontractors of the receipt of that notice.

Under section 32.5(1), a subcontractor paid in full by the contractor on time must, subject to subsection (7), pay each of its own subcontractors no later than 7 days after receiving payment. A subcontractor paid only part of the amount must, subject to the giving of a notice of non-payment, pay each of its own subcontractors the amount paid for their work included in the proper invoice no later than 7 days after receiving payment. If the contractor makes no payment to a subcontractor, and subject to subsections (6) and (7) of section 32.5, section 32.5(5)(b) sets 42 days after the proper invoice was given to the owner as the date by which that subcontractor must pay its own subcontractors.

Payment periods in the Prompt Payment and Construction Lien Act

Who pays whomPeriodCondition from the Act
Owner to contractor (s. 32.2(1))No later than 28 days after receiving the proper invoiceSubject to subsection (2), the owner’s notice of dispute
Owner’s notice of dispute (s. 32.2(2))No later than 14 days after receiving the proper invoiceIn the prescribed form and manner, specifying the amount not paid and all the reasons
Contractor to subcontractor, after full payment (s. 32.3(1))No later than 7 days after receiving paymentSubject to a notice of non-payment under subsection (6)
Contractor to subcontractor, owner has not paid (s. 32.3(4))No later than 35 days after giving the proper invoice to the ownerSubject to subsection (5) or (6); to the extent not paid in full
Contractor’s notice of non-payment (s. 32.3(7))7 days after receiving the owner’s notice of dispute, or before the 35 days expire if none was givenIn the prescribed form and manner, specifying the amount and all the reasons
Subcontractor to its own subcontractors (s. 32.5(5)(b))42 days after the proper invoice was given to the ownerIf the contractor makes no payment to the subcontractor; subject to subsections (6) and (7)
Sources: Prompt Payment and Construction Lien Act (Alberta), sections 32.2, 32.3 and 32.5; Alberta.ca prompt payment rules.

Holdbacks and their release

Alberta.ca says projects that meet a minimum contract value and exceed 12 months in duration will be able to use new rules that allow quicker release of holdbacks. Under those rules, unless the contract allows for progressive or phased releases, holdbacks are released annually. Alberta.ca says the purpose is to ensure holdbacks are not held for more than one year on a multi-year large-scale project.

Alberta.ca says phased or progressive holdbacks must be less than one year. The contract must clearly define the phases, and if there is any ambiguity, the annual release applies.

Section 19(d) of the Regulation lists payment or non-payment of an amount retained as a major lien fund or minor lien fund and owed to a party among the matters a party may refer to adjudication. For a contractor with a large, long project in the ledger, ask the seller which holdback release rule the contract follows and whether any release date has passed.

Adjudication: who runs it and how it moves

Alberta.ca says a subcontractor who has not received payment within the required timeline may issue a Notice of Adjudication to start an adjudication process. Provided they have not already started a court application about the dispute, contractors and subcontractors may submit a notice for adjudication. Section 33.4(1) of the Act says a party to a contract or subcontract may refer to adjudication a dispute with the other party about a prescribed matter. Section 33.4(2) says an adjudication may not be commenced if the notice of adjudication is given more than 30 days after the date of final payment under the contract or subcontract, unless the parties agree otherwise, and section 33.4(3) defines that date. If a party starts a court action on or after the day the dispute is referred to adjudication, section 33.4(5) says both may proceed unless, on the application of a party or on the court’s own initiative, the court directs otherwise.

Notice of Adjudication forms are available from Nominating Authorities. Adjudicators are certified and trained through them. Alberta.ca says ARCANA (AB) and ADACC (Alberta Dispute Adjudication for Construction Contract) are the two Nominating Authorities currently operating in Alberta. At the time the contract is signed, project owners and contractors can choose the Nominating Authority they would prefer to work with in the event of a dispute.

Under section 20 of the Regulation, the party starting adjudication gives the other party a written notice of adjudication. Under section 22, after the notice of adjudication is given to the other party and the relevant Nominating Authority, the parties may, within 4 calendar days, tell the Nominating Authority that they have agreed on an adjudicator, and it must appoint that adjudicator within 7 calendar days; otherwise it appoints a qualified adjudicator within 7 calendar days after the 4 days expire. Under section 23, within 5 days of the adjudicator’s appointment the party who gave notice of adjudication gives the adjudicator a copy of the notice, a copy of the contract or subcontract and the documents it will rely on, and gives all parties copies of those documents.

ARCANA’s adjudication user guide says a response is due within 12 days of receiving the referring party’s submission, or within such other time period as may be directed by the adjudicator. The same guide says binding decisions are typically issued within 30 days of document submissions. The Act’s section 33.6(4) says the adjudicator shall issue a written notice of determination. Under section 33.6(5), the determination of a matter by the adjudicator is binding on the parties to the adjudication, except in the circumstances that subsection sets out.

Under section 30(1) of the Regulation, and subject to subsection (4), a party involved in more than one adjudication may ask the adjudicator conducting the first for consolidation of all adjudications in progress into one. There is no consolidation if more than 5 calendar days have passed since any of the adjudicators gave notice that they had received all the documents and information needed for a determination.

Money held in trust

Under section 22(1) of the Prompt Payment and Construction Lien Act, where a certificate of substantial performance is issued and a payment is made by the owner after it, the person receiving the payment holds that money in trust for the benefit of the persons the recipient owes for the work or materials. Ask a lawyer to look at the payments the contractor received after any certificate of substantial performance.

Government work follows the Public Works Act

Alberta.ca says Alberta government project contracts are subject to the Public Works Act and are exempt from the timelines outlined in the Prompt Payment and Construction Lien Act. The public works fact sheet says the new rules apply to contracts starting on or after April 1, 2025. On those contracts, proper invoices must be given, as applicable, at least every 31 days after the work begins.

The fact sheet says the Crown must pay the undisputed amount no later than 28 days after receiving the proper invoice. A contractor who receives a proper invoice from a subcontractor must pay the undisputed amount no later than 35 days after receiving it, and a subcontractor who receives a proper invoice from its own subcontractor must pay the undisputed amount no later than 42 days after receiving it. Interest under the Judgment Interest Act begins to accrue on any amount owed by any party under a proper invoice that remains unpaid for more than 45 days after the date of receiving it.

The fact sheet says the parties involved can choose to adjudicate a notice of claim under the Public Works Act. If a payment dispute is higher than the legislated amount, it must be resolved through the normal Public Works Act claims process or other contracted provisions, and the fact sheet gives a current maximum for adjudication.

What to check in the receivables ledger before you buy

Go through the ledger project by project and ask for the documents behind each balance. Start with whether each invoice is a proper invoice and whether a notice of dispute was received. For work done for Crown owners, ask which timelines the contract follows.

Then ask for every notice of non-payment given or received, any open adjudication and any determination already issued. For a dispute that has become an adjudication, ask which Nominating Authority is involved and where the matter stands. A determination is binding on the parties to the adjudication, except in the circumstances section 33.6(5) sets out, so ask a lawyer how a determination affects the amounts in the ledger. For related reading, see what to check in accounts receivable before buying and the trades business buyer checklist.

Questions to ask before you buy

  • Which projects in the ledger are under contracts signed after the prompt payment rules applied to them, and which are Alberta government projects?
  • For each unpaid invoice, was it a proper invoice, and was a notice of dispute received?
  • Has the contractor given or received any notice of non-payment, and were its subcontractors told?
  • Are any adjudications open, and has any determination been issued?
  • Is any holdback overdue for release, and which release rule does the contract follow?
  • Were any payments received after a certificate of substantial performance, and who is owed from them?
  • Has a lawyer confirmed the current regulation text, given its recent amendments?

Questions people ask

Short answers; each links to the full page.

What should I check in accounts receivable before buying?
Age them first: a receivable past ninety days is closer to a write-off than an asset, and the aged listing tells you more than the balance-sheet total. Then establish whether receivables are included in the sale at all, who collects them after closing, and what happens to anything uncollected — because silence on that point favours whoever is better advised. Full answer
What is an escrow holdback in a business sale?
In Ontario, a holdback (or escrow) is a portion of the purchase price withheld at closing, or placed with a third party such as a lawyer or trust company, for a defined period after closing. In Ontario, its purpose is almost always to secure the buyer’s post-closing indemnity claims. Full answer
What happens to accounts payable when a business sale closes?
The purchase agreement decides who pays the supplier bills outstanding at closing. It either leaves them with the seller or has the buyer take them on, usually with a matching price adjustment. A few obligations can follow the business regardless, including a supplier’s registered security interest and, in some provinces, unpaid sales tax. Full answer

Related reading

13 pages on the same subject, grouped by topic.

Sources

Every requirement and figure referenced in this guide traces to a primary source. Links were last confirmed on the dates shown.

  1. 01
    Alberta King’s PrinterGovernment
    Prompt Payment and Construction Lien Act, RSA 2000, c P-26.4
    kings-printer.alberta.ca·Checked Oct 24, 2026
  2. 02
    Government of AlbertaGovernment
    Prompt payment rules for the construction industry
    alberta.ca·Checked Nov 19, 2026
  3. 03
    Government of Alberta (Alberta King's Printer)Government
    Prompt Payment and Adjudication Regulation, Alta Reg 23/2022
    kings-printer.alberta.ca·Checked Nov 19, 2026
  4. 04
    Government of AlbertaGovernment
    Industry fact sheet: extending prompt payment to the Public Works Act
    alberta.ca·Checked Nov 19, 2026
  5. 05
    ADR Institute of Alberta (ARCANA)Industry
    ARCANA Adjudication User Guide
    adralberta.com·Checked Nov 19, 2026

Deavo is an advertising and listings platform, not a brokerage, law firm or valuation firm. This page is general information, not legal, tax, accounting or valuation advice, and rules differ by province. Confirm anything you rely on with a qualified professional before you act on it.